m1 (month 1)= March 2024
Milestones – MS
- MS1 (WP1; UT): Artificial neural network using CI and physiological learning trained to perform SH tasks [m21]
- MS3 (WP1; UT): Psychophysical setup established. First series of measurements done [m21]
- MS2 (WP2; KUL): Objective technical and physiological measures for interaural time and level differences are available [m18]
- MS4 (WP2; CBNL): Bimodal fitting. concept defined [m30]
- MS5 (WP2; KUL): Proof-of-concept using braodland (multi-channel) speech or speech-like stimuli [m32]
`
- MS6 (WP3; UT): Audio-tactile training in lab-environment is working and first results published [m24]
- MS7 (WP3; NemoLab): Evaluation of results concerning efficacy of algorithms, training methods and spatial sound technology [m24]
- MS8 (WP4; NemoLab): Identification of key parameters and real-lfe situations to be reproduced in simulation [m12] duplicate
- MS9 (WP4; UCBL) Evaluation of head-movement impact on auditory navigation in NH and NH with enhanced auditory cues [m18]
- MS10 (WP4; UCBL): Evaluation of head-movement impact on auditory navigation in patients with hearing aids (adults and children) [m30]
- MS11 (WP4; UCBL): (Evaluation of most effective visual immersion VR on active auditory navigation (training with head movements) in NH subjects and NH with augmented auditory cues – 1 [m18]
- MS12 (WP4; UCBL) Evaluation of most effective visual immersion VR on active auditory navigation (training with head movements) in NH subjects and NH with augmented auditory cues – 2 [m30]
- MS13 (WP5; NemoLab) Identification of key parameters and real-life situations to be reproduced in simulation [m18]
- MS14 (WP5; ÖAW) Validation of the use of AI to optimise and maxime VR-based training for CI users [m30]
- MS15 (WP5; UNITN) Active movements of the sound source for training SH in seqquential bilateral CI users [m18]
- MS20 (WP5; UNITN): Active movements of the sound source for training SH in seqquential bilateral CI users [m30]
-
MS16 (WP7; UT) Consortium Agreement signed [m2] – April 2024: Achieved
- MS17 (WP7; UT) Planned recruitments completed [m12] – Feb 2025 : Achieved
- MS18 (WP7; UT) Enrolment in PhD program of all Dcs [m15] – Feb 2025: Achieved
- MS19 (WP7; UT) Project mid-term check [m13-m15] -> moved to m20 (October 2025)